Press release

3 Apr. 2017 Calgary, CA

Average Canadian infrastructure project runs 39% over budget and behind schedule by 12 months

According to a new EY report, Spotlight on Canadian power and utility megaprojects, Canadian infrastructure megaprojects run 39% – or US$2.2 billion – over budget and behind schedule by 12 months on average.

Press contact
Sarah Shields

EY Canada Assistant Director, Public Relations

Passionate communicator and writer. Firmly believes Vancouver summers are worth six months of rain.

Power and utilities companies need to control investment in megaprojects

According to a new EY report, Spotlight on Canadian power and utility megaprojects, Canadian infrastructure megaprojects run 39% – or US$2.2 billion – over budget and behind schedule by 12 months on average.

“Canadian power and utilities companies need to act now to start to transform the way they control investment in megaprojects at the local and national levels,” says Gerard McInnis, EY’s Canadian Power & Utilities leader. “If Canada’s going to meet future demand for electricity capacity, the sector will need to significantly invest in power plants, as well as transmission and distribution, for greater development of renewables. They can’t do that with projects running over budget, and behind schedule.”

EY’s report notes that despite the cost overruns and delays, Canadian projects still perform better than those in the US, where the average project delay is a little over three years.

Failure to deliver megaprojects on time and on budget is explained, in part, by the complex and large scale nature of capital project technologies. The report found that globally hydropower and nuclear projects typically suffer the greatest cost overruns at US$4.6b and US$4b, respectively. Meanwhile, offshore wind and gas-powered generation projects saw significantly less delays and cost overruns.

“Canada, more than most countries, already has a diverse mix of energy generation,” says McInnis. “But the mix of how electricity demand will be met, and the size of the investment required, means that defining and controlling capital projects is key if power and utilities in Canada are to create maximum value.”

EY’s report highlights three key challenges the Canadian power and utilities sector faces:

  • Talent constraints with an aging population and inability to attract talent due to international projects where there’s lucrative pay.
  • Unique risk and regulatory environment with standards and codes differing across municipal, provincial and federal levels.
  • Complexity in project governance and managing multiple stakeholders, funding and regulatory compliance.

“Tackling these challenges isn’t necessarily easy,” says McInnis. “But those power and utilities organizations that implement innovate ways to address them, set themselves up to be the sector leaders of the future.”

– 30 –

About EY
EY is a global leader in assurance, tax, transaction and advisory services. The insights and quality services we deliver help build trust and confidence in the capital markets and in economies the world over. We develop outstanding leaders who team to deliver on our promises to all of our stakeholders. In so doing, we play a critical role in building a better working world for our people, for our clients and for our communities.

EY is proudly celebrating 150 years in Canada. For more information, please visit ey.com/ca. Follow us on Twitter @EYCanada.

EY refers to the global organization and may refer to one or more of the member firms of Ernst & Young Global Limited, each of which is a separate legal entity. Ernst & Young Global Limited, a UK company limited by guarantee, does not provide services to clients. For more information about our organization, please visit ey.com.

– 30 –

About EY

EY exists to build a better working world, helping create long-term value for clients, people and society and build trust in the capital markets. Enabled by data and technology, diverse EY teams in over 150 countries provide trust through assurance and help clients grow, transform and operate. Working across assurance, consulting, law, strategy, tax and transactions, EY teams ask better questions to find new answers for the complex issues facing our world today.

EY refers to the global organization, and may refer to one or more, of the member firms of Ernst & Young Global Limited, each of which is a separate legal entity. Ernst & Young Global Limited, a UK company limited by guarantee, does not provide services to clients. Information about how EY collects and uses personal data and a description of the rights individuals have under data protection legislation are available via ey.com/privacy. EY member firms do not practice law where prohibited by local laws. For more information about our organization, please visit ey.com.  Follow us on Twitter @EYCanada.